God has opened a great door of opportunity for Maritime Ministries International in Puerto Rico. The Seafarers International Union recently moved to a new building in San Juan, and donated to MMI their old building. We plan to open a seamen’s mission there as soon as we raise the funds to repair the building. YOU CAN HELP! EVERY GIFT COUNTS! Please go to our secure donation button below to donate.

ESTIMATE OF COSTS 

LOCATION:  FERNADEZ JUNCOS ED. 1057 SANTURCE, PR

LIST OF MATERIALS FOR THE ROOF:

  • Paint rollers, paint brushes, eighteen 5-gallon pails of CROSSCO 8500 roof sealer (@$130.00 each pail), water pressure machine, polymer sealer, hydraulic cement, chainsaw to cut trees.

THE WORK CONSISTS OF:

  1. Removal of existing roofing carton paper.
  2. Wash and clean the roof with water pressure machine. 
  3. Remove asphalt from the roof.  
  4. Leave the roof as clean as possible. 
  5. Seal the cracks with hydraulic cement mixed with polymer sealant. 
  6. Apply roof sealer CROSSCO 8500; Various applications, not more than three.   
  7. Dispose of debris removed from the roof.  

DURATION:  45 DAYS.

ESTIMATE OF LABOR AND MATERIALS:    $20,000.00 

LIST OF MATERIALS FOR THE APARTAMENTS

  • Paint rollers and brushes, paint pans, paint, extensions, scaffolds, bathroom toilets, tiles, kitchen cabinets, air conditioners, electrical systems, floor polishing buffer.  

THE WORK CONSISTS OF:  

  1. Wash the apartments, scrape and Paint the walls and ceiling. 
  2. Remove and install tiles in the bathroom. 
  3. Polish/buff the floors. 
  4. Install kitchen cabinets. 
  5. Install air conditioner, repair the electrical system. 
  6. Install bathroom equipment. 
  7. Obtain electricity certification for each apartment. 
  8. Plumbing certification  
  9. Money deposit for installation of wáter and electricity 
  10. Disposal of the debris 

DURATIÓN OF TIME AFTER ROOF WORK:  60 DAYS

ESTIMATE OF BOTH APARTMENTS:      $50,000.00 

LIST OF MATERIALS FOR THE FIRST FLOOR:

  • Paint rollers and brushes, drop ceiling tiles, bathroom tiles and bathroom equipment, latex and oil paint for the fences, plate glass. 

THE WORK CONSISTS OF:

  1. Wash and polish floors. 
  2. Scrape and Paint floors. 
  3. Remove and install drop ceiling tiles.
  4. Remove and install bathroom tiles. 
  5. Repair the electrical system. 
  6. Repair plate glass. 

ESTIMATE OF FIRST FLOOR WORK:      $18,000.00

WORK OUTSIDE OF THE BUILDING

  • List of materials:  Paint, Paint rollers and brushes, scaffolds.

THE WORK CONSISTS OF: 

  1. Installing the scaffold. 
  2. Wash and Paint external building walls. 
  3. Cut trees. 
  4. Dispose of the debris. 

ESTIMATE OF COSTS:          $15,000.00

DURATION OF WORK:  45 days (depending on the elements of time).

OTHER CHARGES: 

Workmen’s Compensation Insurance; Plumber and Electrician fees;

City permits, if necessary. 

GRAND TOTAL TO REPAIR THE BUILDING:        $103,000.00

This grand total cost can decrease significantly should donations of money and materials be received.   However, many of the items have to be paid, such as the electrical and plumbing systems.  Approximately $30,000.00 are needed for expenses that will not be donated.  For example, insurance, certifications by licensed professionals, equipment that have to be purchased should an emergency arise, and other expenses that may eventually be necessary.